First Article Inspection: What to Request

Request a first article inspection when you need documented evidence that the first parts from the production process meet the drawing before the rest of the order is made.

Agree its scope in the quotation: which features are measured, by which method, how many samples, and which records come with the report. A first article inspection, often shortened to FAI, records a measured result for every requirement on the drawing, or for an agreed set, together with records of the material, finish and process used. It checks the process as well as the part: if the first article conforms, the same process should go on producing conforming parts. Requirements differ by industry and customer. Some sectors define a report format in a standard, such as AS9102 in aerospace, while others use the buyer's own form. The points below are general; the details for your parts are agreed with your supplier.

When Needed

Start with when a first article is needed, because it is tied to changes as well as to the first order.

What a First Article Is and When You Need One

A first article is a part made by the production process, with the intended machines, tooling, material and settings, rather than a hand-made sample or a prototype from another route. Its inspection compares the part with the drawing and records the result for each requirement.

Because it verifies the process, a new first article is usually needed whenever something that could affect the part changes. Common triggers include:

  • A new part going into production for the first time.
  • A new drawing revision that changes dimensions, material or finish.
  • A new mold, a modified or repaired tool, or new fixtures.
  • A change of material grade, material source or manufacturing process.
  • Production moved to another machine or site, or restarted after a long break.

A partial first article can cover only the features affected by a change. Agree in the order which events require a new or partial first article and who decides.

Placeholder for a diagram (BH-A18-S02-I01)

Report Contents

The report is the evidence, so it helps to know what a complete one usually contains.

What the Report Usually Contains

Report formats vary, but a complete first article report connects each requirement on the drawing to a recorded result. Expect it to include:

  • A ballooned drawing, with a number marked against each dimension, tolerance and note.
  • A results table listing each balloon number, the requirement, the measured value and whether it conforms.
  • The measurement method or instrument used for each feature.
  • Material records, such as a material certificate or a certificate of conformance for the grade used.
  • Records of finishes and special processes, such as plating, anodizing, heat treatment or painting.
  • The part number, drawing revision and sample identity, and for molded parts the mold and cavity.

Any result outside the requirement should be shown, not left out, with the action taken or the deviation that was agreed. Each result should trace to a balloon on the drawing revision you released and to the sample that was measured.

Placeholder for a diagram (BH-A18-S03-I01)

Scope

A report that covers every feature is not always what a project needs, so the scope is the next decision.

Agree the Scope Before the Order

Settle the scope with your supplier when you request the quotation. It affects the inspection time, the equipment needed and the price, and two quotes with different scopes are not describing the same work.

All features or critical features

A full first article records every dimension and note on the drawing. A reduced scope covers the features that control fit, function or safety, plus any affected by a change. State which you need, and mark the critical features on the drawing.

Measurement method

Agree how the key features are measured, for example with a coordinate measuring machine, optical measurement, gauges or hand instruments. The datum setup, the part's condition and the measuring temperature can all affect the result, and some plastics change dimension after molding as they cool and absorb moisture.

Number of samples

Agree how many parts are measured. For a multi-cavity mold, decide whether each cavity needs its own first article.

Report format

If you need your own form or an industry format, state it in the order. Otherwise, agree the supplier's format before production starts.

Placeholder for a photo (BH-A18-S04-I01)

Review

When the report arrives, review it together with the parts it describes.

Review the Report and the Sample Together

Review the report against the drawing and the physical parts, not on its own. A report that marks every feature as conforming still needs checking for coverage and traceability.

  • Check that every balloon has a result and that the drawing revision matches the one you released.
  • Read the measured values, not only the pass marks, because values close to a limit may need attention in production.
  • Confirm the sample identity: the part, its revision and, for molded parts, the mold and cavity.
  • Compare the material and finish records with the drawing requirements.
  • Measure or assemble the samples yourself for the features that matter most to your product.

Record the decision in writing: approved, approved with an agreed deviation, or rejected with the features to correct. If a sample is kept as a reference, label it with the report it belongs to.

After Approval

Approval sets the reference for production, and it stays valid only while nothing that affects the part changes.

After Approval: Production and Later Changes

Once the first article is approved, production runs to the same drawing revision, material and process. The approved report, and any retained sample, become the reference for checking later batches.

In production

Agree which features are checked during production and at final inspection, how often, and which records come with each shipment. These checks usually focus on the critical features rather than repeating the full first article.

Later changes

Ask your supplier to tell you before any change to the material, process, tooling or production location, and agree when a new or partial first article is needed. A change made without notice can leave the approved report no longer representative.

Repeat orders

Reference the approved drawing revision and first article in each repeat order, so the parts are made against the same baseline.

Your Enquiry

All of these choices can be written into your request before the first parts are made.

Include First Article Requirements in Your RFQ

State the first article requirement in your request for quotation, so it is planned and priced with the parts:

  • The drawing and its revision, with the critical features marked.
  • Whether you need a full or reduced first article, and the number of samples.
  • Any required report format or industry standard.
  • The material, finish and process records you need with the report.
  • The changes that will require a new first article, such as a revision or a tool change.

Ask each supplier to state the first article scope in its quotation. Bohui produces CNC machined and injection molded parts in its own factory, and you can include your inspection requirements when you send the design.

Discuss the Requirement with Bohui

Share the part information and the decision you need to make.

Placeholder for a contact photo of Jane

Jane

BOHUI PROTOTYPES LIMITED

I'm Jane, the contact for your enquiry.

You can also reach me by email or on WhatsApp.

Jane

BOHUI PROTOTYPES LIMITED

  • Address: Xiaobian Street, Chang'an Town, Dongguan City, Guangdong Province, China

Request a Quote

Fields marked  are required.

Jane BOHUI PROTOTYPES LIMITED Privacy Policy